FIREFLY® Systems Upgrade Compartmentation For Nottingham Health Centre

CASE STUDY — HEALTHCARE SECTOR
Meadow Heath Health Centre — Roof Space Fire Compartmentation Retrofit
LOCATION: Nottingham, East Midlands
SECTOR: Healthcare / NHS
ACCREDITATION: FIRAS Certified
We delivered a rapid, fully certified passive fire compartmentation upgrade within the complex roof-spaces of an active NHS health centre — completing the works on time, with zero disruption to ongoing clinical operations.
THE CHALLENGE
Bringing a Busy Health Centre Up to Code
The Meadow Heath Health Centre in south-east Nottingham was undergoing a significant merger of two GP practices under the direction of Nottingham City Clinical Commissioning Group. During preparatory surveys, it became clear that the fire compartmentation within the building's extensive roof-space had fallen out of compliance.
The combination of the building's age, previous alterations carried out over the years, and updates to fire regulations under Approved Document B meant that existing fire-stopping measures no longer met current standards. Issues with the original installation, compounded by subsequent damage, required a comprehensive and technically precise upgrade to restore compliant compartmentation and prevent the risk of fire "burn-over."
Non-compliant roof-space compartmentation
Damage to original fire-stopping installation
Complex roof geometry requiring bespoke details
Live healthcare facility — minimal disruption required
Tight two-week programme
Regulatory context
Approved Document B compliance
BS EN 1363-1:2022 (fire resistance testing)
BS EN 1364-2 (non-loadbearing elements)
FIRAS scheme accreditation required
Protected zone specification: 1,500mm either side of wall
OUR APPROACH
A Designed Solution, Not Just an Installation
Following a detailed inspection of the roof-space, we worked in close consultation with FIREFLY® Technical Manager Chris Boam to develop a design solution tailored to the specific geometry and compliance requirements of the building. Rather than a standard fix, a fully engineered compartmentation system was proposed — one that addressed both the structural complexity and the need for long-term certified performance.
Our four-man team completed all works within the agreed two-week programme, installing FIREFLY® Zeus Lite 90:30 vertical and horizontal barriers in combination with the FB180 Ablative Batt system to create protected zones extending 1,500mm either side of each wall. Batts were mechanically fixed and finished with intumescent mastic and brush-applied ablative coating. FIREFLY® FR120 Access Hatches were also installed to provide compliant access to the upgraded compartments.
"Some issues with the original installation and subsequent damage meant the compartmentation required significant improvement and we made use of the FB180 Batt system to ensure that any fire cannot break through and cause burn-over. It was a technically complex job, and the work went quite smoothly — the whole job is certified under our FIRAS scheme accreditation."
Daniel Oldacre, Contracts Manager — Krasi Fire Protection
OUTCOME
Certified, Compliant, On Time
Full Approved Document B compliance restored across all roof-space compartments
90 minutes integrity and 30 minutes insulation achieved
All works certified under our FIRAS scheme accreditation
Contract completed within the agreed two-week programme
Compliant roof-space access maintained via FR120 Access Hatches
Zero disruption to ongoing clinical operations at the health centre






